NWSC-3 RFP | NCAR'S NEXT-GENERATION HPC PROCUREMENT

Schedule

The key milestones and dates for the NWSC-3 procurement (RFP000074) are provided in the following table. Note that these dates are provided as a general guideline only and do not represent a commitment by UCAR.

Milestone Estimated Date         Date Completed
Benchmark code and input cases released 24 Jul 2019 19 Jul 2019
Draft Technical Specifications (DTS) released 15 Aug 2019 15 Aug 2019
DTS comments and feedback due 03 Sep 2019 03 Sep 2019
NWSC-3 Request for Proposals (RFP) released 02 Apr 2020 02 Apr 2020
RFP Q&A period 03 Apr through 01 May 2020 01 May 2020
Deadline for vendors to notify UCAR of attendees for the NWSC Virtual Site Visit (due by 1700 Mountain Daylight Time/MDT) 20 Apr 2020 20 Apr 2020
NWSC Virtual Site Visit for vendors 24 Apr 2020 24 Apr 2020
Deadline for vendors to submit RFP questions (due by 1700 MDT) 01 May 2020 01 May 2020
All vendor RFP questions answered by UCAR 08 May 2020 08 May 2020
Deadline for vendor proposals (due by 1500 MDT) 29 May 2020 29 May 2020
Subcontract awarded Q1 2021 Pending
System delivery Oct 2021 Pending
System acceptance Dec 2021 Pending
Production 03 Jan 2022 Pending